PLC BASED INTELLIGENT TRAFFIC CONTROL SYSTEM
ABSTRACT
The main object of this study was to design and implement
intelligent traffic control system. The system developed is able to sense the
presence or absence of vehicles within certain range by setting the appropriate
duration for the traffic signals to react accordingly. By employing mathematical
functions to calculate the appropriate timing for the green signal to
illuminate, the system can help to solve the problem of traffic congestion.
Hardware simulation tests were successfully performed on the algorithm
implemented into a PLC (programmable logic controller). The new timing scheme that
was implemented promises an improvement in the current traffic light system and
this system is feasible, affordable and ready to be implemented especially
during peak hours, off hours and pedestrians. The PLC checks the status of the
sensors. The system resolution is depend on the output provided by the sensors,
Then PLC checks the priorities and then provide output signal to the traffic lights
poles for ON or OFF the Red, yellow or Green lights and ON time is depend on
the specific priorities. The roads are opened in that manner that east road,
west road, north road and then south road is open.
INTRODUCTION
Traffic load is highly dependent on parameters such as
time, day, season, weather and unpredictable situations such as accidents,
special events or construction activities. If these parameters are not taken
into account, the traffic control system will create bottlenecks and delays. A traffic
control system that solves these problems by continuously sensing and
monitoring traffic conditions and adjusting the timing of traffic lights
according to the actual traffic load is called an intelligent traffic control
system. Traffic control systems may also be classified as saturated or unsaturated,
depending on whether they were designed for a saturated or unsaturated network.
In an unsaturated network, it is desired to minimize the mean delay of drivers,
while in a saturated network it is desired to serve as many drivers as
possible, or in other words, to maximize traffic capacity of the intersection.
The problem of capacity maximization is the same as the queue minimization problem.
The older system uses weight as a trigger mechanism.
Current traffic systems react to motion to trigger the light changes. Once the infrared
object detector picks up the presence of a car, a switch causes the lights to
change. An adaptive traffic control system must have the ability to diagnose saturation
conditions in the network and change the objective function as desired. In
older fixed-time systems, there were multiple timing plans, but now a modern
traffic control system can have multiple control strategies.
We need to understand the function of traffic signals so
that we can improve driving habits by controlling the speed in order to reduce
the number of associated traffic accidents. The more number of drivers who know
about the operation of traffic signals, the less frustrated they are going to
be while waiting for the lights to change. The main aim in designing and
developing of the Intelligent Traffic Signal
Simulator is to reduce the waiting time of each lane of
the cars and also to maximize the total number of cars that can cross an intersection
given the mathematical function to calculate the waiting time. The Intelligent
Traffic signal Control System consists of three important parts. The first part
is the PLC controller and second part is hardware. These usually comprise of
red, yellow, and green lights. The third part is the sensor. The sensors check
the presence of vehicles.
OVERVIEWOF PLC BASED ITCS
The main theme of this report is to build and verify the
designs and understand the concept. The main objective is to build a hardware device
that has:
1. The ability to collect the information of the busy tracks
by sensors and providing the output to PLC.
2. The ability to take decision against the information and
change the time according to the priorities.
Traffic Control System
- Traffic signals control vehicle movements
- Traffic Control Systems are interconnected with electronics system that controls traffic signals.
- Traffic Control Systems depend on logic which can be divided into these categories:
- The signal phases and cycle length are depend on the traffic flow on the desired track
- The system responds to interrupts or timing base system and open the desired signal according to the priority requirement
Advantages
- Traffic signals help control the flow of vehicles, pedestrians and bicycles by giving “right-of-way” to the various movements in an orderly manner. Signals that are properly located, designed and maintained can:
- Provide for orderly movement of traffic.
- Increase capacity of the intersection.
- Reduce frequency and severity of certain types of crashes, especially right-angle collisions.
- Provide for continuous movement of traffic at a definite speed along a given route.
- Interrupt heavy traffic at intervals to permit other vehicles or pedestrians to cross.
- Effectively perform traffic management
- Overall, traffic signals help us get where we’re going safely and in a timely manner.
Disadvantages
- Traffic signals are sometimes considered problems at intersections. In fact, traffic signals that are poorly located can adversely affect the safety and efficiency of vehicle, bicycle and pedestrian traffic. Improper or unjustified signals can result in one or more of the following:
- Significant increase in the frequency of some types of collisions
- Increased congestion, air pollution, and fuel consumption
- Excessive delay.
- Excessive disobedience of the signal indications.
- Increased use of less adequate streets as motorists attempt to avoid the traffic signals.
- Frustration especially in hot weather.
What is Intelligent Traffic Control System (ITCS)?
An Intelligent Traffic Control System senses the presence
or absence of vehicles and reacts according to the sensors output. In this
system PLC takes a data from sensors and checks the priorities. After that PLC
provides signal to traffic signals.
The intelligent traffic control system works in four different
modes are Normal flow, peak time, off time and manual operation. Peak time and
off time modes are depended on the sensors outputs then change the status. Our
intelligent traffic control system totally depend on the sensors output and
take decisions.
Study overview
This study has two main parts. First is study of PLC and
the second part is its application intelligent traffic control system. The
intelligent traffic control system has further divided into two main parts, Programming
and hardware. Ladder logic Programming technique is used. PLC T100MD2424+ is
used for attaching with proto type hardware. In hardware photoelectric sensors
is used for sensing the presence the vehicles on the square in proto type.
What is PLC?
A PLC (Programmable Logic Controller) is a device that
was invented to replace the necessary sequential relay circuits for machine
control. The PLC works by looking at its inputs and depending upon their state,
turning on/off its outputs. The user enters a program, usually via software,
that gives the desired results
Practical System Design
Practically Inductive Loops are used as sensors to detect
the presence of vehicles on intersections. Its basic function is to provide
interrupts to controller unit. It has two parts, first is coil and second is
the detector unit. Coil is a main part of a sensor and consists of one or more
loops of wire embedded in the pavement. This inductive coil is connected with
the detector unit, which is an electronic circuit. When vehicles passes over or
rests on the inductive loop then due to induction on vehicle more current flow
through inductive loop and this change of current also changes frequency. Detector
unit can detect these changes. Finally, detector unit sends an interrupt signal
to controller unit.
Prototype Hardware
In prototype design Photo electric sensors are used, for
prototype it is not possible to design an induction loop. As the basic function
of induction loop in Intelligent Traffic Control System is used to provide an
interrupt signal to controller unit. We use Photo electric sensors rather than
induction loops. In our design, photo electric sensors provide an interrupt
signal to controller unit. In case when vehicle reaches in front of sensors,
then it provides an interrupt.
Flow diagram of traffic
System block diagram
SIMULATION
Tool
TRILOGI software has built in simulator engine. It is
used without attaching the PLC hardware. This is the main advantage of the TRILOGI
software. This type of feather is not used in other software
Advantages of TRILOGI software
The main advantage of the TRILOGI software has it’s built
in simulator engine that provide us the facility to simulate the program any
time without attaching the plc module. We check our all priorities, inputs,
interrupts, timers, relays, counters and its output status in live condition.
This is the big advantage of TRILOGI software.
PLC simulator
- Trilogy has built in simulator engine which is in effect a “soft PLC”
- Great ease of program testing and debugging
- Test run of program off-line directly on the same pc that runs TRILOGY
- Program can be distributed amount students to run that at home and test their logics without the need of PLC
- Remotely program, monitor, control and troubleshoot your super PLC controlled equipment via the internet at any time
- Remote software update
- PLC can e-mail specific reports at required time
- PLC can send SMS with just a single line of code
HARDWARE IMPLEMENTATION
Hardware Components
1. PLC T100MD module
2. Interface card
3. Photoelectric Sensors
4. Signal poles
5. Communication Ports
6. Toggle Switches
7. Proto type hardware
PLC T100MD module
T100MD2424+ is a new member of the highly popular T100MD PLC family. The
basic unit comprises 8 analog I/Os, 24 digital Inputs and 24 digital outputs.
Two of the digital outputs (7 & 8) which can be also defined as PWM outputs
can each deliver up to 10A peak and 2A continuous, 24VDC (active high) current
to the load. The 8 analog I/Os are configurable as 8 AI, no AO or 6 AI and 2
AO. All analog inputs are 10-bit resolution and all analog outputs are 8-bit resolution.
T100MD2424+ is expandable up to a total of 96 digital inputs and 96 digital
outputs with an optional expansion module. It has an RS232 and an RS485 port.
Both of them are conversant in MODBUS protocol. The built-in LCD port allows
simple interface to industry standard LCD modules from 8 characters to 80
characters.
The compactly designed T100MD2424+ PLC can be easily installed in many
kinds of plastic or metal enclosures. You need to use 4 or 5 PCB standoffs (or
some screws and nuts) to support the controller and fasten it to a console box.
Analog I/O Ports: The 8 channels of analog I/Os are available via an 8-way
detachable screw terminal connector along the left edge of the T100MD2424+ PLC.
The PLC also supplies a +5V analog reference-voltage output
Digital I/O Ports:
Detachable screw terminals are provided for quick connection to all digital
inputs, outputs and power supply wires. Each block of screw terminals can
easily be detached from the controller body, enabling easy replacement of the
controller board when necessary. Since the terminal block for digital I/Os are inserted
vertically to the board surface, you need to remove the terminal block before
you can start wiring. Use a small flat-head screwdriver and insert underneath
the terminal block, apply even pressure to raise the terminal block until it
becomes loosened from the connecting-pin strip, as shown below:
Although wires of up to 24 AWG may be connected directly to the screw
terminal, insulated crimper rules should be used to provide a good end
termination to multithreaded wires. Use of crimper rules reduces the
possibility of stray wire- strands short circuiting adjacent terminals and
their use is therefore highly recommended.
The T100MD2424+ PLC requires a single regulated, 12 toc24V (+/- 5% ripple)
DC power supply for the CPU and I/Os (as shown in Figure 1). It is recommended
that whenever possible, use a higher power supply voltage since the voltage difference
between ON and OFF state is wider for operation at higher voltage. To use the
T100MD2424+ at 12VDC you should place a jumper block on the two-pin header
marked “J1-12V” near the power supply terminals. You must remember to remove
the jumper when operating the PLC above 18V. Otherwise the voltage regulator
may overheat. Please use only industrial
grade linear or switching regulated power supply from established manufacturers.
Using a poorly made switching power supply can give rise to a lot of problems
if the noisy high frequency switching signals are not filtered properly. If
your application demands very stable analog I/Os you should choose a linear
power supply instead of a switching power source for the CPU. Always place the
power supply as near to the PLC as possible and use a separate pair of wire to connect
the power to the PLC. Keep the power supply wires as short as possible and
avoid running it alongside high current cable in the same cable conduit. The
T100MD-2424+ PLC will be reset when the power supply voltage dips.
Interface card
The interface card is used between the sensors output and PLC for interfacing.
In this card we use opto coupler is used for short the two pins i.e. pin # 1
and pin # 25. When the input is approaches from sensor then a current limiting
resistor is used for reducing the current and drops the voltage for a specific
limit. When sensors provide output then a resistor is used in series with the opto
coupler and the output terminal of the opto coupler is attached with pin no 1
and lower terminal is connected with pin no 25. When the opto coupler gains
supply at its input then the output terminal is short and behaves like a
switch, so PLC receive a interrupt from pin no 1 and then take decision about
that.
Symbol of opto coupler
Interface card
We use single opto couplers for each input with a resistor and use 8 inputs
that represent 8 sensors. These opto couplers are connected from pin # 2 to pin
# 9.
Photoelectric Sensors
We use photo electric sensors for sensing the presence of the vehicle on
the road. We use industrial based sensors has variable range that can be adjust
by a variable knob at its surface. It has built in transmitter and receiver.
This sensor works on PNP condition means that when object is placed in the
range of sensor then it provides output. It has 3 output wires, one is used for
input supply, and second wire is common between input and output. Third wire is
used as output when object is detected.
Inductive Loops (Practical System)
Loop detector technology has become the most widely used sensor in incident
detection systems. They are capable of measuring flow and occupancy, and
estimating vehicle speed. They can also be used to actuate traffic control
devices and detect congestion and incidents. An inductive loop detector
consists of one or more loops of wire embedded in the pavement and connected to
a control box, excited by a signal ranging in frequency from 10 KHz to 200 KHz.
When a vehicle passes over or rests on the loop, the inductance of the loop is reduced
showing the presence of a vehicle. The raw data supplied by inductive loop
detectors are vehicle passage, presence, count, and occupancy. For incident detection,
loop data is usually relayed to a controller for analysis.
Signal Poles
It is a device that indicates the status of the signal. The purpose of signals
poles to ON or OFF lights (Red, Yellow, and Green). Its timing depends on the
input given by the PLC according to the timing of the programming priorities.
One signal open at a time and all other signals are stopped. Each signal light
is a combination of four LEDs, two are connected in series and two are
connected in parallel.
Communication Ports
The latest revision (Rev. D or D-1) of the T100MD+ features two independent
serial ports that can simultaneously communicate with other devices using a variety
of protocols. They can also be programmed to accept or send ASCII or binary
data using the TBASIC built-in commands such as INPUT$(n), INCOMM (n) , PRINT
#n, OUTCOMM n, d The first serial port (COMM1) is an RS232C port which is
compatible with most PC RS232C ports. The second serial port (COMM3) is a two wire
RS485 port that allows multiple PLCs to be connected to a single host computer or
a master PLC for networking or to implement a distributed control system.
Proto type of Intelligent Traffic Control System
In this system black color shows the road and white dashes shows the separation
between the two way traffic. The black poles basically the signals poles
heaving Red, Yellow and Green LEDs for showing the signals. In the figure Blue
color rod basically the photoelectric sensors that checks the presence of the
vehicle. Each row has two sensors; first sensor is placed near the signal pole
and the second sensor is placed away from the first sensor. We use total eight sensors
for our system. The model of our design is shown
Proto type of intelligent Traffic Control
System
CONCLUSION
An intelligent traffic light system had successfully been designed and developed.
The sensors were interfaced with Lab PLC Module. This interface is synchronized
with the whole process of the traffic system. This prototype can easily be
implemented in real life situations. Increasing the number of sensors to detect
the presence of vehicles can further enhance the design of the traffic light
system. Another room of improvement is to have the infrared sensors replaced
with an imaging system/camera system so that it has a wide range of detection
capabilities, which can be enhanced and ventured into a perfect traffic system.
REFERENCES
1. Alan J Crispin, 1997,”Programmable Logic Controller and their
Engineering applications”, second edition.
2. John W. Webb and Ronald A. Reis, “Programmable Controller, Principles
and application”.
3. Neil M. Schmitt and Robert F. Farwell,”Understanding Automation System”.
4. W. Bolton, 2000, “Programmable Logic Controllers”. Second edition.
5. Solomon, S., 1999. Sensors Handbook. McGraw- Hill, New York.
6. A.A. M.A. A. M. HIRARI. Et al. (2006), “Design and Development of sensor
based traffic light system.” American Journal of Applied Sciences 3: 1745,
1749.